Title: FEATURES OF OPTIMIZING THE CALENDAR SCHEDULE OF OPEN-PIT MINING BY STEEPLY INCLINED LAYERS

FEATURES OF OPTIMIZING THE CALENDAR SCHEDULE OF OPEN-PIT MINING BY STEEPLY INCLINED LAYERS
Serik Moldabayev; Zhanat Sultanbekova; Madiyar Sarybayev; Tolegen Adil; Madinur Akhmetova
10.5593/sgem2022/1.1
1314-2704
English
22
1.1
•    Prof. DSc. Oleksandr Trofymchuk, UKRAINE 
•    Prof. Dr. hab. oec. Baiba Rivza, LATVIA
The transition to mining benches with transverse panels from top to bottom within the boundaries of steeply inclined layers does not allow transforming the results of mininggeometric analysis sequentially for each individual stage of mining into a calendar schedule of mining operations. Therefore, a model is offered for converting the results of mining-geometric analysis into a calendar schedule of mining operations with sequential mining of benches from top to bottom using phased volumes of overburden rocks and ore reserves of adjacent steeply inclined layers. Each next stage of mining includes ore reserves of the previous steeply inclined layer and volumes of overburden rocks of the adjacent steeply inclined layer. In this case, the time of simultaneous mining of ore reserves and overburden in adjacent steeply inclined layers is assumed to be equal and should ensure the fulfillment of the annual design volumes of ore extraction. A reduction of overburden excavation, due to a significant increase in the slope angle of the pit walls of the steeply inclined layers, is achieved with the provision of independent high-rhythmic overburden and mining operations even on round shaped open pit fields. The studied technology of mining benches transverse panels in steeply inclined layers below the thickness of loose overburden rocks could improve technological development of deep and ultra-deep open pit mines, especially with combined motor-conveyor transport. Optimization of the calendar schedule of mining operations when mining rock overburden and ore with transverse panels in steeply inclined layers was performed at the ultra-deep Kacharsky open pit mine.
[1] Moldabayev S.K., Adamchuk A.A., Toktarov A.A, Aben Ye., Shustov O.O. Approbation of the technology of efficient application of the excavator-automobile complexes in the deep open mines // Naukovyi Visnyk Natsionalnoho Hirnychoho Universytetu (Scientific Bulletin of the Open Mining University), 2020. - № 4. – рр. 30- 38 https://doi.org/10.33271/nvngu/2020-4/030.
[2] Moldabayev S.K., Sdvizhkova O.О., Babets D.V., Kovrov O.S., Adil T.K. (2021). Numerical simulation of the open pit stability based on probabilistic approach. Naukovyi Visnyk Natsionalnoho Hirnychoho Universytetu, 186(6): 29-34. https://doi.org/10.33271/nvngu/2021-6/029.
[3] Dryzhenko A.Y. (2011). Phased mining of rocks overburden of iron ore open pit mines with steeply inclined excavation layers. Mining journal, 2, pp. 25-28. http://rudmet.ru/journal/482/article/4585/
[4] Shustov O.O., Haddad J.S., Adamchuk A.A., Rastsvietaiev V.O., Cherniaiev O.V. (2019). Improving the Construction of Mechanized Complexes for Reloading Points while Developing Deep Open Pits. Journal of Mining Science, 55, 946-953. DOI: https://doi.org/10.1134/S1062739119066332
[5] Gavrishev S.E., Kolonyuk A.A., Burmistrov K.V. (2007). Features of the design and depreservation of temporarily non-active pit walls. Mining informational and analytical bulletin, # 2, pp. 272-275.
[6] Anisimov, O., Symonenko, V., Cherniaiev, O., & Shustov, O. (2018). Formation of safety conditions for development of deposits by open mining. E3S Web of Conferences, 60. https://doi.org/10.1051/E3SCONF/20186000016
[7] Kuznetsov D.V., Kosolapov A.I. Optimization of parameters of technological complexes of ore open pit mines: monograph. – Krasnoyarsk: Siberian federal university, 2020. – 188 p.
[8] Gavrishev S.E., Burmistrov K.V., Burmistrova I.S., Rakhmangulov A.N., Kidyayev V.A., Tomilina N.G (2015). Evaluation of the effectiveness of the use of technological schemes for ore transportation while mining of beyond contour reserves of the deposit. Mining informational and analytical bulletin, #4 (15), pp. 131-139.
[9] Sinchkovskyi V.N., Vokin V.N., Tenyashnikov V.A. (2006). Formation of the working zone of open pit mines considering the depreservation of temporarily non active pit walls. Mining informational and analytical bulletin, # 3, pp. 306-307.
[10] Dryzhenko A.Y., Kozenko G.V., Rykus A.A. (2009). Open-pit mining of iron ore in Ukraine: state and ways of improvement: Monograph. Dnepropetrovsk: NMU, 452 p.
[11] Drebenstedt C., Ritter R., Suprun V.I., Agafonov Y.G. (2015). World experience in the operation of cyclic and continuous method complexes with in-pit crushing. Gornyi journal, #11, pp. 81-87. doi: 10.17580/gzh.2015.11.17.
[12] Miller S.O., Kholodnyakov G.A. Methodology of justification of calendar planning at Kuzbass open pit mines // Mining informational and analytical bulletin. – M.: Gornaya kniga, 2015. – Special edition # 19. - pp. 30-36.
[13] Kholodnyakov D.G., Loginov E.V. Management of the mining regime and the slope angle of active open pit wall // Mining informational and analytical bulletin. – M.: Gornaya kniga, 2015. – № 2. - pp. 71-74.
conference
Proceedings of 22nd International Multidisciplinary Scientific GeoConference SGEM 2022
22nd International Multidisciplinary Scientific GeoConference SGEM 2022, 04 - 10 July, 2022
Proceedings Paper
STEF92 Technology
International Multidisciplinary Scientific GeoConference SGEM
SWS Scholarly Society; Acad Sci Czech Republ; Latvian Acad Sci; Polish Acad Sci; Serbian Acad Sci and Arts; Natl Acad Sci Ukraine; Natl Acad Sci Armenia; Sci Council Japan; European Acad Sci, Arts and Letters; Acad Fine Arts Zagreb Croatia; Croatian Acad Sci and Arts; Acad Sci Moldova; Montenegrin Acad Sci and Arts; Georgian Acad Sci; Acad Fine Arts and Design Bratislava; Turkish Acad Sci.
281-288
04 - 10 July, 2022
website
8419
ore open pit mine, steeply inclined layer, round shaped open pit field, calendar schedule of mining, mathematical modeling