ASSESSMENT OF POWER GENERATION LOSSES FOR GOLESTI HYDROPOWER PLANT, ROMANIA, DUE TO A RESERVOIR MANAGEMENT PLAN REQUIRED BY EUTROPHICATION

Assist. Prof. Dr. Liana Ioana Vuta, Assoc. Prof. Dr. Bogdan Popa, Assoc. Prof. Dr. Gabriela Elena Dumitran, Assist. Drd. Eliza-Isabela, Assist. Prof. Dr. Florica Popa

First published: 2017-06-20https://doi.org/10.5593/sgem2017/42/s17.011View metrics

Abstract

This paper presents an assessment of power generation losses of a hydropower plant (HPP) due to an imposed reservoir management plan and comparisons in terms of monetary value with the existing management plan but with an eutrophic reservoir. The study case is represented by Gole?ti reservoir, which is a shallow reservoir in Romania, and the associated HPP. Gole?ti reservoir is an artificial lake of medium size, which has a 55пїЅ106 m3 volume and a maximum depth of 32 m. Its use is complex: it allows flood control, hydropower generation, household and industrial water supply and irrigation. Thus, it prevents downstream flooding for a 50 km2 area, it provides a flow of 156 m3/day for Bucharest (domestic and industrial) and 9 m3/s for irrigation of a 100 km2 area, it is secondary source for industrial water supply of Pitesti City (up to 6 m3/s) and it's also used for electricity generation in the associated HPP Gole?ti having an installed capacity of 8 MW. A previous study has concluded that, for the optimal operation of Gole?ti reservoir, both energetically and environmentally, it is recommended a frequent use of the bottom discharge. The result was a management plan which requires the use of the bottom discharge every 2 weeks, at least 1 hour at 20 m3/s and at least once every 2 years, at least 1 hour at maximum flow, in order to flush sediments and to avoid reservoir clogging. In this context, the present study aims to introduce these hypotheses into the reservoir management plan, in order to assure a proper quality of water, and to assess the power generation losses in terms of electricity production.

Publication Impact Profile

PlumX
  • Citations
  • Scopus - Citation Indexes: 1
  • Captures
  • Mendeley - Readers: 2

Publication details

Title
ASSESSMENT OF POWER GENERATION LOSSES FOR GOLESTI HYDROPOWER PLANT, ROMANIA, DUE TO A RESERVOIR MANAGEMENT PLAN REQUIRED BY EUTROPHICATION
Authors
Assist. Prof. Dr. Liana Ioana Vuta, Assoc. Prof. Dr. Bogdan Popa, Assoc. Prof. Dr. Gabriela Elena Dumitran, Assist. Drd. Eliza-Isabela, Assist. Prof. Dr. Florica Popa
Proceedings
SGEM International Multidisciplinary Scientific GeoConference EXPO Proceedings; 17th International Multidisciplinary Scientific GeoConference SGEM2017, Energy and Clean Technologies
Publisher
STEF92 Technology
Year
2017
Pages
83-90
SWS Citekey
Popa2017178390
ISSN
1314-2704
ISBN
978-619-7408-07-2
Language
en
Publication type
Conference Paper
Keywords
References0
0references registered for this publication

Structured references will appear here after the reference import pass. The count is preserved now so the scholarly record is not incomplete.

View or Download full articleAccess options
Full paper accessChoose SWS login, librarian support, or instant article download.

SWS access login

Login as SWS Scientific Committee

Authors and approved SWS contributors will read and export their own linked papers after identity matching by SWS profile, email and SGEM GlobalID.

For librarian assistance: [email protected]

Purchase Instant Access

48-hour online accessComing soon
Online-only accessComing soon
Download the full article in PDF formatEUR 35
  • Article can be downloaded after successful payment.
  • Article may be used according to SWS library access terms.
  • Article cannot be redistributed.
Get full paper

Back to publication list