CONSOLIDATION OF A ROCK FILL EMBANKMENT CONSTRUCTED ON SOFT CLAYS
(STEF92 Technology, 2018-06-20, Corina Chiotan)
Show more
For one motorway project in Romania, the alignment has to cross an artificial lake that was made for drying a former swamp. The alternatives considered were crossing the lake with a bridge or with an embankment. According to the geotechnical investigations, the soil in the area consisted of soft saturated clays of 10-18m followed by marle. Crossing the lake with a bridge involved raising the vertical alignment of the motorway to nine meters above ground level in order to ensure the clearance for the maintenance of...